The most helpful resource in the preparation guide is the PRINCE2 Foundation Practice Exam. Once the candidate believes they are adequately prepared, they can take the practice test. The practice exam will assist the candidate in identifying their weak points so that they may work on them. Try 10 PRINCE2 Foundation exam sample questions below to know where you stand!

1. What information should be recorded in the quality register?

A. Planned activities to determine whether the products are fit for purpose
B. Potential threats to the project’s objectives and how they will be managed
C. Lessons that the project will capture and use during the project
D. Off-specifications that will occur during the project

Answer: A

2. The objective of Starting up a Project process is to

A. Identify who will be responsible for creating the Project Plan
B. Agree on how the project will be monitored and controlled after initiation
C. Authorize the Project Manager to proceed with the initiation stage
D. Agree how issues and changes will be identified, assessed, and controlled

Answer: A

3. How does the Controlling a Stage process support the focus on products principle?

1. Using a formal procedure to manage change
2. Continually reviewing the planned benefits against the actual benefits
3. Including Product Descriptions in Work Packages agreed with the Team Manager 4. Recording and comparing the status of products completed during the stage

A. 1, 2, 3
B. 1, 2, 4
C. 1, 3, 4
D. 2, 3, 4

Answer: C

4. Identify the missing word(s) in the following sentence: The Quality Theme provides a set of rules and procedures that ensure that the [?] created meet the project’s needs.

A. controls
B. products
C. Project management team
D. stages

Answer: B

Contact us for more PRINCE2 Foundation study materials!

5. Which may be funded from a risk budget?

A. Corrections due to off-specifications
B. Impact analysis of requests for change
C. Implementation of a fallback plan
D. Preparation of the Risk Management Strategy

Answer: C

6. Which should be provided by a project mandate?

A. Terms of reference
B. Detailed Business Case
C. Stage tolerances
D. Initiation Stage Plan

Answer: A

7. Which of the following is the purpose of the Starting up a Project process?

A. Decide if it is sensible to initiate the project
B. Ensure the communication requirements of all stakeholders are documented
C. Learn lessons from the project
D. Document how changes required by corporate or program will be reviewed

Answer: A

8. Which of the following are PRINCE2®️ Principles?

1. Continued business justification
2. Defined roles and responsibilities
3. Risk management
4. Learn from the experience

A. 1, 2, 3
B. 1, 2, 4
C. 1, 3, 4
D. 2, 3, 4

Answer: B

9. What should be recorded in a Quality Register?

A. Reference to any documented actions required to correct errors found in reviewed products
B. Quality criteria against which each product is to be measured
C. Handover arrangements to be followed when a product has been approved
D. Full details of any requested changes to a product during a quality inspection

Answer: A

10. Which of the following is NOT part of quality planning?

A. Define quality responsibilities
B. Gain acceptance of the project product
C. Agree on acceptance criteria
D. Set quality tolerances

Answer: B

PRINCE2-Foundation Exam Passing Secrets

If you’re worried about your PRINCE2-Foundation test and aren’t prepared, you don’t have to be. Get the most recent PRINCE2- Foundation exam dumps with 100% accurate answers. SPOTO will help you pass your PRINCE2 Foundation exam on the first try!

Latest SPOTO Candidates Pass Feedback

Last modified: 2021-09-26

Author

Comments

Write a Reply or Comment

Your email address will not be published.