Have you kept up with the latest updates to the PMBOK guide’s project management practices in its sixth edition? If so, this is your time to demonstrate your knowledge. This PMP exam contains free PMP 6th edition exam questions identical to those found on the PMP certification exam. The PMBOK test is an excellent stepping stone toward the critical PMP certification exam, as it is designed to assist you in passing the exam on your first attempt. What are you waiting for, then? Try out the free PMP 6th edition practice exam!

Related Read:

Download Free PMP Exam Questions and Answers for 2021-PMBOK 6th

Part 2: Download Free PMP Exam Questions and Answers for 2021-PMBOK 6th

Question 21

According to Tuckman, which of the following is not one of the stages of team development?

A. Delegating

B. Performing

C. Forming

D. Norming

Answer: A

Question 21 Explanation: According to Tuckman, the stages of team development are Forming, Storming, Norming, Performing, and Adjourning.

Question 22

You are reviewing the earned value analysis of your project, and you see the following information:

Earned Value = $500,000

Actual Cost = $550,000

Planned Value = $600,000

According to this information, what is the status of your project?

A. Ahead of schedule and over budget

B. Ahead of schedule and under budget

C. Behind schedule and under budget

D. Behind schedule and over budget

Answer: D

Question 22 Explanation: SV = EV − PV

SV = 500,000 − 600,000

SV = $−100,000

Since SV is negative, the project is behind schedule.

CV = EV − AC

CV = 500,000 − 550,000

CV = $−50,000

Since CV is negative the project is over budget.

Question 23

Which of these is an output from the Acquire Resources process?

A. Organizational chart

B. Project team assignments

C. RAM

D. Staffing Management Plan

Answer: B

Question 23 Explanation: After determining elements such as the roles and responsibilities, reviewing recruitment practices, and negotiating for staff, project team members are assigned to project activities as part of the Acquire Resources process.

Question 24

Which one of the following is not an input to the Develop Project Charter process?

A. Stakeholders Register

B. Agreements

C. Business Case

D. Organizational Process Assets

Answer: A

Question 24 Explanation: Inputs of the Develop Project Charter process are:

Business Case

Agreements

Enterprise Environmental Factors

Organizational Process Assets

Question 25

Which one of the following is not an output of the Direct & Manage Project Work process?

A. Change Requests

B. Deliverables

C. Project document updates

D. Work Performance Reports

Answer: D

Question 25 Explanation: Work Performance reports are an output of the Monitor and Control Project Work process, while the results of the Direct & Manage Project Work process are:

Deliverables

Work Performance data

Issue log

Change requests

Project management plan updates

Project document updates

Organizational process assets updates

Question 26

As a project manager involved in the Control Procurements process, you know that early contract termination is a particular case of procurement closure. The instances of exceptional procurement closure can result from all of the following except?

A. Cause or convenience outside the terminations clause of the contract

B. Convenience of the buyer provided in the contract

C. Default of one party

D. Mutual agreement of both parties to terminate

Answer: A

Question 26 Explanation: Early termination of a contract is a particular case of procurement closure that can result from a mutual agreement of both parties, from the default of one party, or for the buyer’s convenience if provided for in the contract. The rights and responsibilities of the parties in the event of early termination are contained in a terminations clause of the agreement.

Question 27

The cost baseline is developed during which process?

A. Determine budget

B. Develop schedule

C. Monitor & control project work

D. Estimate costs

Answer: A

Question 27 Explanation: The cost baseline or project budget is developed in the Determine Budget process, a planning process in project cost management.

Question 28

Which statement about the critical project path is valid?

A. The critical path has zero total floats, and it shows the earliest possible time to complete the project

B. The critical path has zero or negative total float

C. A project can have only one critical path

D. The critical path consumes the biggest portion of the project budget compared to other paths

Answer: B

Question 28 Explanation: The critical path can have a negative total float if there is a constraint set on the project finish date.

Question 29

While acquiring your project team, you realize that a specific consultant is required to be on your team according to the project charter. This consultant has particular knowledge, and your client has dictated that you hire him as a team member. This situation describes which one of the tools and techniques of the Acquire Resources process?

A. Negotiation

B. Virtual Teams

C. Multicriteria Decision Analysis

D. Pre-Assignment

Answer: D

Question 29 Explanation: Pre-assignment involves selecting project team members in advance. When specific people were promised as part of the project proposal, the project is dependent on the expertise of particular persons, or staff assignments are defined within the project charter.

Question 30

You are assigned as the manager of a vast multi-billion dollar infrastructure project for three years. You are working in the planning process group of your project, and currently, you are creating the project WBS. Due to lack of information, you decide to make the WBS of the project’s commissioning phase (which is the last phase) in more detail later on when you have more information. This approach to creating the WBS is also known as:

A. Progressive planning

B. Waterfall planning

C. Rolling wave planning

D. Agile planning

Answer: C

Question 30 Explanation: Rolling wave planning involves planning near-term items in greater detail than those further off in time.

Are you prepared to sit for the PMP® Exam? Take a look at the results of your mock exams!

This has been demonstrated with a significant number of Aspirants. You are now prepared to take the exam if you achieve a score of at least 75% on quality sample exams.

Yes, passing the exam is equivalent to passing, as the certificate does not indicate whether you scored competently or somewhat proficient on all questions.

If you’re still unsure and want to gain further hands-on experience before sitting for the real PMP® test, check out SPOTO PMP 100% Real Exam Dumps, which has been extensively updated to reflect the PMP® Exam’s current updates in 2021!