The PMI Certified Associate in Project Management (CAPM®) is an entry-level project management qualification. This course is intended for those with little or no project experience. Attending the CAPM® online assessment test is the first step toward project management success. Prepare yourself for the greatest practice experience.

Related Read:

Download Latest 100% Real PMI-CAPM Exam Questions Demo

Part2: Free CAPM Exam Questions and Answers | Test Your Preparation for the CAPM Exam

QUESTION 1

Impacts to other organizational areas, levels of service, and acceptance criteria are typical components of which document?

A. Business case
B. Work breakdown structure
C. Requirements documentation
D. Risk register

Correct Answer: C

QUESTION 2

Units of measure, level of precision, level of accuracy, control thresholds, and rules of performance measurement are examples of items that are established in the:

A. Cost management plan.
B. Work performance information.
C. Quality management plan.
D. Work breakdown structure.

Correct Answer: A

QUESTION 3

An electronics firm authorizes a new project to develop a faster, cheaper, and smaller laptop after improvements in the industry and electronics technology. With which of the following strategic considerations is this project mainly concerned?

A. Customer request
B. Market demand
C. Technological advance
D. Strategic opportunity

Correct Answer: C

QUESTION 4

Which process in Project Time Management includes reserve analysis as a tool or technique?

A. Estimate Activity Resources
B. Sequence Activities
C. Estimate Activity Durations
D. Develop Schedule

Correct Answer: C

QUESTION 5

A tool and technique used during the Define Scope process is:

A. facilitated workshops.
B. observations.
C. questionnaires and surveys.
D. group creativity techniques.

Correct Answer: A

QUESTION 6

Which tool or technique is used in validating the scope of a project?

A. Facilitated workshops
B. Interviews
C. Inspection
D. Meetings

Correct Answer: C

QUESTION 7

Which is a communication method used in the Report Performance process?

A. Expert judgment
B. Project management methodology
C. Stakeholder analysis
D. Status review meetings

Correct Answer: D

QUESTION 8

In the Initiating Process Group, at what point does the project become officially authorized?

A. When the project charter is signed
B. When all the stakeholders agree on the scope of the project
C. When the project manager is appointed
D. When the necessary finance or funding is obtained

Correct Answer: A

QUESTION 9

Who is responsible for determining which processes from the Process Groups will be employed and who will be performing them?

A. Project sponsor and project manager
B. Project sponsor and functional manager
C. Project manager and project team
D. Project team and functional manager

Correct Answer: C

QUESTION 10

Which of the following are outputs of Develop Project Team?

A. Human resources plan changes and project staff assignment updates
B. Project management plan updates and enterprise environmental factor updates
C. Resource calendars and project management plan updates
D. Team performance assessments and enterprise environmental factor updates

Correct Answer: D

Conclusion

The Certified Associate in Project Management (CAPM®) course provides beginners with an understanding of key project management principles, five process groups, and 10 knowledge areas as defined by the Project Management Institute (PMI)®. Your CAPM® certification demonstrates that you have a fundamental understanding of project management principles, terminologies, and processes. SPOTO offers legitimate and up-to-date PMI CAPM test questions in skillfully produced CAPM dumps to assist you in preparing for and passing the CAPM exam on the first attempt!