Are You a PMP® Certified Professional? Take Our Free Test Immediately

Preparing for an exam in 2021 can be difficult at times, much more so when there is a great deal to learn in a short period of time. SPOTO PMP® exam dumps, which contain actual exam questions, are the excellent resource for regularly preparing and assessing your preparation level. It assists with PMP® exam preparation online by familiarizing you with the PMP® testing paper’s style and scope.

For your preparation, here are ten recent and authentic exam questions! Now, feel free to give it a try!

get 100% pass dumps

Further Reading:

2021 100% Latest PMP Practice Test 1

11. A temporary endeavor undertaken to create a new product or service is called a:

A. Project
B. Program
C. Enterprise
D. New product development

Explanation

Option A is the correct answer as it is the correct definition of a project accordingly to PMI.

12. Any numbering system that is used to monitor project costs by category such as labour, supplies, or materials, for example, is called:

A. Work breakdown structure
B. Universal accounting standard
C. Standard accounting practices
D. Chart of accounts

Explanation

Chart of accounts is the correct answer (option D). All other options are invalid for this question.

13. The purpose of the review of deliverables and project performance at the conclusion of a project phase is to:

A. Determine how many resources are required to complete the project according to the project baseline.
B. Adjust the schedule and cost baselines based on past performance.
C. Obtain customer acceptance of project deliverables.
D. Determine whether the project should continue to the next phase.

Explanation

At the end of a project phase, deliverables and project performance are evaluated to determine if the project should continue to the next phase. Option D is the correct answer.

get 100% pass dumps

14. The stakeholder analysis matrix is part of:

A. Part of the Stakeholder Management Strategy – an output of identify stakeholders.
B. An output of Plan Communications.
C. Part of the stakeholder register.
D. Part of Performance Reporting.

Explanation

The stakeholder analysis matrix is part of Stakeholder Management and is an output of identify stakeholders. Option A is the correct answer.

15. Which of these is a constrained optimization project selection method?

A. Number programming
B. Murder board
C. Dynamic Programming
D. Parallel algorithm

Explanation

Only Dynamic Programming is constrained optimization project selection method. Option D is the correct answer.

16. The Delphi Method is best suited for:

A. Decision-making
B. Cost Control
C. Overhead rate estimating
D. Team discussions

Explanation

Option A is the correct answer. The Delphi method is normally used for Decision Making, the option options are not valid answers.

17. A rough order of magnitude estimate is made during which project management process group?

A. Project closing
B. Project executing
C. Project initiating
D. Project planning

Explanation

“Rough order of magnitude estimates are used during the initial phases of the project in the Project initiation group. Option C is the correct answer. During project closing, the overall cost of the project is already known. Also, budget is already known during the executing phase. More accurate estimates are generated during the planning stages.”

18. You are using straight line depreciation to compute the value of your computer after three years. If the current cost is $1000, what will be the value after three years assuming that the computer’s life is five years.

A. 400
B. 500
C. 600
D. 0

Explanation

Option A is the correct answer. “The value of a computer workstation that is worth $1000, depreciated over 5 years will be worth $400 after 3 years using straight line depreciation. $1000 / 5 years = $200 per year. 3 years x $200 = $600 depreciation after 3 years $1000 – $600 = $400 current value”

19. You are the Project Manager assigned to build a next generation vehicle. You identify a dependency that the wheels must be designed and developed before the assembly of the vehicle can be performed. This is an example of which type of dependency?

A. Discretionary
B. Soft Logic
C. Mandatory
D. External

Explanation

This is a mandatory dependency; option C is the correct answer.

20. A schedule performance index (SPI) of 0.76 means:

A. you are ahead of schedule.
B. you are only progressing at 76% of the rate originally planned.
C. you are only progressing at 24% of the rate originally planned.
D. you are over budget.

Explanation

SPI of 0.76 indicates that the project is behind schedule and progressing at 76% of the original plan. Option B is the correct answer.

Summary

To pass the PMP® exam in 2021, you must erase all doubts and practice thoroughly using SPOTO PMP Exam Dumps. SPOTO PMP® exam dumps aid you in developing the ideal test-taking approach by doing a detailed analysis of your performance. SPOTO PMP® practice questions enable you to assess yourself at any time and from any location, boosting your confidence, overcoming your blunders, and enhancing your speed and accuracy. Provide an immediate boost to your preparations with our PMP® exam dumps!

Are you looking for additional Free PMP Exam Practice Tests? Contact us!

get 100% pass dumps

Latest SPOTO Candidates Pass Feedback

Last modified: 2021-11-03

Author

Comments

Write a Reply or Comment

Your email address will not be published.